When a plant manager says the line is expensive to run, the answer is almost always in one of four columns. Get those four measured and the argument about machine price disappears.

1. Power

Measure kWh at the meter over a weighed tonnage. A double-shaft shredder on mixed commercial waste typically lands at 8-14 kWh per tonne. If you are above 20, the machine is running empty or the counter-knife gap is wrong.

2. Wear parts

Blades, screens and counter-knives, expressed per tonne. On rigid plastic this is often below 0.40 USD; on C&D with rebar it can pass 1.20 USD. A single number here tells you whether your feed is contaminating the machine or your supplier is.

3. Labour

Count everyone who touches the line, including the loader driver and the person swapping bins. A line that needs three people because the discharge is manual will out-cost a more expensive machine that needs one.

4. Downtime

Hours lost per month multiplied by the value of a lost tonne. This is the column nobody measures and the one that dominates. Two unplanned days a month on a 10 t/h line is roughly 160 tonnes of lost output.

Putting them together

A workable benchmark for mixed waste shredding is 4 to 9 USD per tonne all-in, excluding depreciation and disposal. If your number is double that, look at downtime first, wear parts second, and the machine third.