Plant quotations usually start with tonnes per hour. On construction and demolition waste, the more useful first question is what share of the feed is reinforced concrete - because rebar decides the crusher, the magnet arrangement and the maintenance interval.
Clean demolition rubble with light mesh can go straight to an impact crusher. The product is cubical, the reduction ratio is high, and one magnetic stage after crushing is enough to meet most recycled aggregate specs.
Heavily reinforced concrete needs a jaw crusher upstream. A jaw tolerates the steel, but the rebar does not disappear - it comes out of the discharge as tangled bundles that wrap around belts and block transfer chutes. Budget for a magnet over the jaw discharge, not only after the secondary crusher.
Ask a supplier what share of rebar they assume in the tonnage figure. If the answer is vague, the capacity figure is optimistic. A plant rated at 150 t/h on clean rubble may hold 100 t/h on reinforced concrete, and the difference is what shows up in month two.
The practical approach: sample the feed for a week, weigh the steel recovered, and size the crusher on the tonnage that remains after the magnet. That is the number the plant actually processes.